IS_​READY_​FOR_​ISSUE

Tekla Structures
2019i
Tekla Structures

IS_​READY_​FOR_​ISSUE

The IS_READY_FOR_ISSUE attribute tells if the drawing has been marked ready for issuing in Document manager. This attribute can be used for adding Document manager information about drawings marked for issuing in drawing reports. The report returns the value 1 if the drawing is marked ready for issuing, and 0 if it is not marked ready for issuing.

The Document manager has a columnReady for issuing for this information. If the drawing has been marked, there is a check mark in the column.

To include in the report who has marked the drawing ready for issuing, use the attribute READY_​FOR_​ISSUE_​BY. This information is shown in the Ready for issuing by column in Document manager.